Hoboken Road Work Schedule — August 26-28
Summer continues, and so does Hoboken Road Work…
From the City of Hoboken:
PSE&G will begin the second phase of milling and paving work to repair trenches created during the installation of new gas mains as part of the Energy Strong program. Work on additional streets will be announced in the near future. Parking will be prohibited on both sides of the street during milling and paving.
Milling is scheduled to take place August 26, 2015 through August 28, 2015, weather permitting, on the following streets:
• 6th St from Jackson St to Hudson St
• Willow Ave from 6th St to 11th St
• Garden St from 11th St to 14th St
• 12th St from Bloomfield St to Willow Ave
• 13th St from Bloomfield St to Garden St
• 14th St from Washington St to Willow Ave
PSE&G is working to complete repairs on these roads prior to the start of the school year. Temporary No Parking signs are posted on these streets for August 26th through August 28th. Once milling work is completed on a street, the No Parking signs on that street will be taken down and parking will be permitted on that street.
Paving of these streets is scheduled to take place the week of August 31, 2015. The schedule is weather permitting and subject to change.